Vladivostok, July 17, 2015, 03:54 – REGNUM In Primorye can not find the culprit in the failure of the state program of gas supply and gasification of the region. Currently under threat is the construction of Tore “St. Michael” and “Nadezhdenskaya” as well as the project of the Free Port of Vladivostok. According to one version, the cause is the lack of activity of the administration of Primorye, the correspondent IA REGNUM .

Read also: Putin legitimized the free port of Vladivostok

The company “Gazprom Mezhregiongaz” (included in “Gazprom”) was on the territory of Primorsky Krai the construction of trunk and gas pipelines and gas distribution stations. In turn, the regional administration is obliged to ensure synchronization construct local distribution pipelines, preparation for gas supply houses, and boiler. At the same schedules are generated every year taking into account the financial possibilities of Primorye.

The Acting Director of the Department of Energy edge Denis Kutsenko said that “the program of gas supply and gasification of the Primorsky Territory for 2012-2015″ has already disrupted. The blame put officer at JSC “Gazprom”, which allegedly have not started construction and installation works on any object.

The governor of Primorye Vladimir Miklushevsky , in turn, said that he intends to replace the contractor LLC “Gazprom Mezhregiongaz” and with the assistance of the prosecutor’s office to bring the company in the register of unfair suppliers. At the same time in his words, terms of gasification Tore jeopardizes projects. About problematic situation Vladimir Miklushevsky intends to report presidential envoy in the Far East Yury Trutnev , Chairman of the Government Dmitry Medvedev , and possibly the head of state Putin .

In turn, the company “Gazprom Mezhregiongaz” argues that the contractor for the construction of objects is not: the company is in the territory of Primorye investment. The program of gasification of the region is carried out in view of its financial possibilities. Thus, the press service of the company told IA REGNUM was informed that to date yet completed three gasification facilities, whose total length is more than 61 kilometers. However, the administration of Primorye are still not fulfilled its obligations: the nine boilers for gas produced only seven.

«The issue of advanced gasification areas of socio-economic development” Nadezhdenskaya “and” St. Michael “in the Primorsky Territory was first raised at a joint meeting with Minvostokrazvitiya Russia in Moscow in April 2015. According to preliminary results of the meeting determined the amount and timing of the projects were subsequently held working meetings with representatives of the administration of the Primorsky Territory, Vladivostok. Getting these projects provided the documents, which are currently under consideration in the administration of the region “, – stated in” Gazprom Mezhregiongaz “.

The company also claims that the Primorye administration still has not provided revised data that are necessary to determine the parameters of gas supply and gasification of tori. Not adjusted timing scheme, and are not prepared tender documentation and design objects.

«In accordance with the Urban Planning Code, the design is based on the project planning and land survey, the preparation of which is the responsibility of the regional administration. However, the lack of activity of the Primorsky Territory Administration in the preparation of planning projects and surveying virtually paralyzed the completion of the design and transfer of project documentation to the authorities Glavgosekspertizy that does not allow the start of construction of the current year “, – stressed the representatives of the company.