Head Federal Air Transport Agency held a meeting at which he expressed concern about the pace of work general contractor.
« would like to remind you once again to our terms to the schedule to ensure the commissioning of the new runway. In general, since the beginning of January it made quite noticeable progress. But we remain the same timeline – On June 1, we have to take off from the new runway , – said Alexander Neradko. – But neither the object is not ready yet, the documentation is not issued, do not forget that the certification will take time. Every day we are monitoring the situation on the number of people and equipment, which are involved here at the facilities. There must be 238 people and work in two shifts, I drove here today, so many are not counted. If this were true, slippage and could be reduced. ”
Alexander Neradko demanded by the general contractor of FSUE “General Directorate of roads and airfields during Spetsstroy Russia” as a priority, to complete the laying of communication lines and power supply to all the radio facilities. To do this, put about 850 meters of cable connection and set the order of 100 joints.
«” Spetsstroy “it is necessary to complete this work until 5 April, I would ask them to focus very much on as the delay associated with the laying of the cables will result in a shift of all subsequent works. Your subcontractors in the period April 15, must complete all commissioning work at radio sites, by May 1, you must obtain permission to enter the facility, and until May 30 – Get ready documents for the implementation of take-off and landing strip », – said Alexander Neradko.
According to him, in late March, “Kamchataeronavigatsia” to complete the commissioning and within a month to make necessary operational tests. Since May 1, air traffic management must be carried out already with a new control tower.
«During this month to do a tremendous amount of work. I hope that by the time we will need to “fly around” this band all the necessary documents are ready. Because construction readiness – that’s not all – added the governor of the region Vladimir Ilyukhin. – Kamchatka need this airport, Kamchatka need this band, it is the summer, when people massively fly on holiday, and will be the maximum load on the airport services. You all know very well that the old band is in critical condition. ”
During the meeting, the head of the Federal Air Transport Agency and the governor of the region discussed the prospects of development of airport infrastructure in the districts of the region, including the construction and reconstruction of airports and air terminals, provided by the federal target program “Economic and social development of the Far East and the Baikal region to 2018 “. Particular attention was paid to the reconstruction of airports Palau and Ossory.
in Palana on schedule before the end of August the general contractor must complete the work on the installation of light-signaling equipment, the construction of fuel storage, patrol roads and fences, power supply system. Contents permits for entry into operation of the platform “Spetsstroy” shall, before the end of May.
Until the end of 2016 should be upgraded airport Ossora. In summer, the contractor plans to begin construction of a new terminal building in the village. Also during the summer season in the village will be delivered plates for the runway, and will begin work on its reconstruction. During the meeting the head of the region expressed concern that the contractor does not have time to carry out the planned work in time and offered to move them to the winter, when the load of the airport is much smaller. Proposals for the reconstruction of the complex in Ossora Federal State Unitary Enterprise “General Directorate of roads and airfields during Spetsstroy Russia” must submit before April 15. According to preliminary data, the reconstruction of the complex can be done in stages, and to close the airport for a period of work would be required.
In 2016, work on the modernization of airport facilities will be developed in 4 areas of Kamchatka. Reconstruction is planned in Ust-Kamchatsk airports Ozernoi, Sobolev, Ust-Khairyuzovo. In accordance with the developed projects there equip new runways, aprons, taxiways, terminal buildings will be built, will perform a set of other measures aimed at improving the comfort and safety of air traffic. Also, in 2016 to begin construction of a new terminal building in the village of Nikolskoye Aleutian area.
At the end of the meeting, together with the Federal Air Transport Agency of the PCF “Airports of Kamchatka” develop proposals for the further development of the network of the northern edge of the airport.
Let’s remind, the progress in the completion of the reconstruction of the runway at the main airport in Kamchatka is on the personal control of the head of Sergei Ivanov, the Russian President Administration. During a working visit to the region in September 2015, he held a meeting on the reconstruction of the airport complex, which has criticized the general contractor – Federal State Unitary Enterprise “General Directorate of roads and airfields during construction Spetsstroy Russia.” He demanded complete all construction works to 30 May 2016.
Reconstruction of the runway at the airport Yelizovo started on behalf of Russian President Vladimir Putin. For these purposes from the federal budget has been allocated about 12 billion rubles.